RTA financial and project status report – March 2025

RTA Project Status – Through March 10
Projects in design 80
Under construction/implementation 74
Total number completed 1,048
RTA Financial Status – Through March
Funds expended to date $1.67 B

Over 1,000 RTA projects completed, including:

  • 202 of 200 intersections promised (two additional intersections added)
  • 83 of 80 pedestrian crossings promised (two additional crossings added)
  • 180 of 200 bus pullouts promised
  • 183 of 250 miles of new sidewalks promised
  • 370 of 550 miles of new bike lanes promised
  • 18 roadway corridor completions
    • Also, 11 roadway corridors partially completed

Over 66% of all the RTA plan improvements to date (since 2006) are within the City of Tucson. Additionally, over 62% of RTA transit offerings are to enhance transit services within the City of Tucson.